Best Practice Tip – UAT Action Plan

Spread the love

One of the most crucial steps in System Development Life Cycle (SDLC) is User Acceptance Testing (UAT), a type of system and business objective validation, performed by the end users, and business objective sign off by the project owner; not to be confused with System Testing

Spread the love

One of the most crucial steps in System Development Life Cycle (SDLC) is User Acceptance Testing (UAT), a type of system and business objective validation, performed by the end users, and business objective sign off by the project owner; not to be confused with System Testing which is performed by the Ivanti Developer and/or ISM Administrator

Many Ivanti Service Manager implementations fall short when it comes to proper UAT Testing, be it due to a lack of resources, time, or budget, but more often than not due to a shortcoming of proper UAT Action Plan and UAT Test Cases and Scripts.

Today we will focus on a sample high level UAT Action plan:

  • Refresh UAT with PROD (ISM Administrator)
  • Push Asset Scanner Packages to UAT (ISM Consultant)
  • Create UAT Test Cases/Scripts (ISM Administrator/Knowledge Manager; with assistance from ISM Consultant)
  • Create Documentation for ISM Users (ISM Administrator/Knowledge Manager with assistance from ISM Consultant)
  • Test Data Preparation (ISM Administrator)
  • Test Run (ISM Administrator)
  • UAT Run (ISM Administrator+ Storage Managers)
  • Remediation (ISM Consultant)*
  • UAT Run (ISM Administrator+ Storage Managers)*
    • Including Validation of Documentation and Knowledge Article Creation (ISM Administrator/Knowledge Manager)  
  • Confirm Business Objectives – Sign Off (Project Owner)
  • Schedule Push to PROD (ISM Consultant)
  • Communication Plan (Core Team)
    • ISM Change Control Announcement
    • ISM Change Control Email with Documentation
      • Determine schedule
        • Before – for example 3 days before
        • At PROD Push
        • After – optional – follow up 
  • PROD Push (ISM Consultant)
  • Validate PROD Push (Core Team)
  • PROD Emergency Support – 1 to 2 hours after push – (ISM Consultant)

By Freelance ITSM Consultant

Freelance Consultant, Developer since 1996 with 100+ ITSM/ITAM/ESM Implementations

Extensive Implementation Experience with ITSM products such as but not limited to Ivanti Neurons, Ivanti Service Manager, and HEAT ITSM

Past Customers include Fortune 500 & Global 500 Enterprise Clients, Frontrange Business Partners, Ivanti Business Partners, and private Swiss banks.

Roles and Responsibilities from Project Management, System Architecture, Design, Development, Consulting (technical & functional)

Worldwide in the UK, Europe, Australia, New Zealand, South Korea, Singapore, Canada, and the USA

Disclaimer: Not endorsed by, affiliated with, or sponsored by Ivanti
"Ivanti Consultant" refers to job description, experience, and skill set with Ivanti's product line and is merely descriptive of the fact that I have experience with Ivanti's ITSM products.

I have never been directly employed by Ivanti,

I have been employed by Frontrange Business Partners and sub-contracted by Ivanti Business Partners to work with Ivanti Project Managers and/or Ivanti Implementations